South Africa is considering a major nuclear expansion, but energy specialists are divided over whether the country needs the capacity and can afford to build it.
Image: AI Generated
South Africa wants to add 5 200MW of nuclear power by 2039 and is considering a broader 10 000MW programme to rebuild its nuclear industry. But energy specialists are questioning whether the country needs that much new capacity, whether it can afford the projects and whether it has the capacity to deliver them.
The Integrated Resource Plan (IRP) 2025 provides for 5 200MW of new nuclear generation by 2039. Government is also developing a Nuclear Industrialisation Plan to assess the case for a wider 10 000MW programme, aimed at rebuilding the country’s nuclear fuel-cycle industry.
At a recent EE Business Intelligence (EEBI) webinar, Zizamele Smodeni Mbambo, the Department of Electricity and Energy’s deputy director-general responsible for nuclear energy, outlined the thinking behind the expansion.
Mbambo said government wanted to restore capabilities across the nuclear fuel cycle, from uranium conversion and enrichment to fuel fabrication, power generation and waste management.
“Studies have demonstrated that a 10-gigawatt nuclear power programme will provide the scale that’s needed to justify the local nuclear fuel cycle facilities,” Mbambo said.
He argued that the programme could strengthen energy sovereignty while supporting industrialisation, localisation, mineral beneficiation, skills development and job creation.
But the proposed expansion has raised questions about electricity demand, the cost of nuclear construction and the country's ability to manage projects of this scale.
Professor Mark Swilling of Stellenbosch University’s Centre for Sustainability Transitions said decisions about new generation capacity needed to take account of changes in South Africa’s electricity landscape.
“The most distinctive feature about our energy transition is that we’ve shifted from peak load shedding in 2023 to curtailment in 2026,” he said.
Swilling was referring to periods when electricity supply exceeds demand, particularly during the middle of the day when solar generation is high and some power has to be curtailed. He argued that this made flexibility increasingly important, including battery storage and gas backup.
He also questioned the demand projections underpinning the proposed nuclear capacity.
“Net electricity generation today is about 225 terawatt hours, roughly the same as it was 20 years ago in 2005,” he said.
While modelling anticipates electricity demand rising substantially by 2040, Swilling cautioned that previous projections had also expected growth that did not materialise.
“The question is, will we need 5 200 megawatts of nuclear by 2040, especially if we take into account what it may cost?” he asked.
The financial risks, he argued, extend beyond the initial construction budget. Referring to international research on nuclear construction costs, Swilling said: “The overall conclusion was that there was a negative learning curve. In other words, as learning curves went up, prices didn’t come down as usual. And in fact, the costs doubled.”
He pointed to projects in the United States, France and the United Kingdom where costs had escalated, and questioned whether South Africa had the capacity to manage a project of similar complexity.
“Our own history, Medupi and Kusile, which Chris has documented, is definitely not a good example or doesn’t confirm that we have the necessary capacity to deliver these large projects on time,” he said.
Energy analyst Matthew Cruise of Jaltech questioned the broader 10GW ambition, arguing that government had not demonstrated that the proposed scale was justified by South Africa’s electricity-system needs.
He suggested the target appeared to be driven more by the desire to rebuild the domestic nuclear industry than by evidence of future electricity demand.
“The 10GW figure seems to have come from the advice of vendor countries, not from our own system needs,” he said.
Cruise cautioned against committing to a large nuclear programme partly to create a market for locally produced nuclear fuel.
“I would be cautious about building more reactors partly to create a market for locally produced nuclear fuel,” he said.
He also raised concerns about the long lead time and financial exposure involved, warning that substantial capital could be tied up for years before a new plant began generating electricity.
“My concern is how much capital is committed upfront when the first electrons to flow from Nuclear are about a decade away,” he said.
“Financial interest builds up during construction, and delays leave consumers paying higher tariffs or taxpayers covering guarantees.”
Cruise further argued that South Africa should prioritise investment in transmission infrastructure, renewable energy and battery storage, particularly given the constraints on connecting additional generation to the grid.
Independent energy analyst Tshepo Kgadima offered a contrasting perspective, arguing that the debate should not be reduced to whether nuclear power is expensive, but should consider the country's long-term energy security and industrial development.
“What is the actual projected electricity demand, on an electricity consumption per capita per year basis, does South Africa need for the next forty to fifty years?” he asked.
He argued that electricity was central to reversing South Africa’s deindustrialisation and questioned whether government was adequately considering the strategic implications of its energy decisions.
“The real question is not whether South Africa needs nuclear power and the capacity thereof but rather whether the Minister has any comprehension of the geostrategic and geoeconomic implications of energy and specifically electricity for a developing country that has suffered years of deindustrialisation,” Kgadima said.
While supporting nuclear as part of a reliable electricity mix, he argued that new generation projects should not place further financial pressure on the state.
“Funding for electricity supply buildout projects should never go onto the country balance sheet and be financed through the fiscus,” he said.
Government says the proposed programme is moving towards public consultation.
Electricity and Energy Minister Kgosientsho Ramokgopa recently revealed that Eskom had submitted its feasibility report for the 5 200MW programme.
The department is preparing a proposed section 34 determination for public participation, which he intends to publish before June 2027.
“The Department is preparing the proposed determination for public participation. We will put the case for the additional capacity before the public and consider submissions on their merits,” Ramokgopa said.
He also acknowledged that financing and construction timelines would have consequences for consumers.
“For new nuclear, the cost of capital and the time it takes to build will influence what users ultimately pay,” he said.
South Africa's existing nuclear programme and proposals for further development have been the subject of previous debate, including plans for a new nuclear power station at Duynefontein, near Koeberg.
The country's nuclear ambitions have also included proposals to expand local reactor manufacturing and the nuclear fuel cycle, including the revival of the Pebble Bed Modular Reactor programme.