Out of 683 stalled housing projects countrywide, 233 came to a standstill for periods ranging from five years up to more than 10.
Image: Ayanda Ndamane / Independent Newspapers
Human Settlements Minister Thembi Simelane has revealed that out of 683 stalled housing projects, 233 have come to a standstill for periods ranging from five years up to more than 10.
The department also faces a title-deed backlog of more than 1.2 million, some dating back to pre-1994.
Responding to DA MP Matlhodi Maseko, Simelane said her department has compiled preliminary information from provincial project registers and human settlements business plan schedules covering different reporting periods.
“The information identifies projects that have remained incomplete for extended periods. However, the reported categories have not in every case been verified against the original contractual completion date and approved extensions of time,” she said.
Her response showed that there were 43 projects that came to a standstill for periods ranging between five and nine years, 46 for a period of 10 years and 144 for more than 10 years.
The Free State has the highest number of stalled projects at 81, followed by the Eastern Cape with 55, Gauteng 34, North West 27, KwaZulu-Natal 16, Limpopo 13, Western Cape five and one each in the Northern Cape and Mpumalanga.
Simelane said the reason for the stalling of the projects varied by project.
“Provincial reports identify poor contractor performance, abandonment of sites, defective workmanship, contract disputes and terminations, inadequate bulk infrastructure, funding constraints, community disruptions, unlawful occupation and delays relating to beneficiary approvals, land and title documentation.”
She said the department did not yet have a verified consolidated national amount of expenditure recovered in cases in which delays were found to be unreasonable.
“Recoveries must be confirmed from the records of the relevant implementing and contracting authorities, including any penalties, guarantees, damages, settlements or amounts actually recouped. The absence of a consolidated figure does not establish that no recoveries have occurred,” she said when asked about the amount recovered from contractors where delays in construction of houses were found to be unreasonable.
Simelane would not say how many contractors were flagged for trading with the State, including blacklisting.
“The available submissions also do not establish a verified national number of contractors referred for further action, including restriction or blacklisting. The relevant provincial or municipal contracting authorities are responsible for applying contractual remedies and initiating any applicable restriction or other consequence-management procedures, subject to the prescribed requirements,” she said.
While claiming that her department performed its policy, coordination and oversight responsibilities under the Housing Act, Simelane underlined the importance of a consolidated report on the stalled housing projects.
“The reconciliation of provincial project registers, expenditure and recovery records, and contractor-related actions is necessary to provide an accurate consolidated account of delayed projects and progress towards their completion. The provincial departments continue to prioritise the blocked project in their annual business plans with the intention to revive them for completion.”
Simelane’s response comes almost five months after she acknowledged that blocked housing projects present a serious risk to service delivery, value for money and the credibility of the human settlements programme.
She has previously said a forum of the Human Settlements Minister and MECs had taken a decision that the blocked projects should be treated as a priority across all provinces.
Simelane had said a R582 million has been set aside to address the blocked projects in the 2026/27 financial year.
“All provinces continue to prioritise the unblocking of blocked projects as part of improving service delivery and protecting public investment.”
Meanwhile, the minister said there were 27 475 title deeds backlog for the pre-1994 period, 413 986 for the post 1994-period and 787 786 post 2014 era.
Simelane noted that the process that resulted in the registration of a title deed involved township proclamation, installation of bulk and internal services, beneficiary verification and dispute resolution.
“The total costs associated with the entire property transfer process vary across projects and categories based on the project-specific details,” she said
Simelane put the costs for the property transfer at R92.5 billion for resolving the property-transfer process generally.