The Social Housing Regulatory Authority says it plans to have the 9378 units in 17 social housing projects unblocked completed by December 2028.
Image: DEPARTMENT OF HUMAN SETTLEMENTS
The Social Housing Regulatory Authority (SHRA) said yesterday it would need nearly R700 million to unblock nearly 20 blocked and incomplete housing projects that have come to a standstill.
Briefing the Human Settlements Portfolio Committee SHRA said it plans to have the 9378 units in 17 social housing projects completed by December 2028.
SHRA executive Biansha van Staden said the entity has a portfolio of 65 housing projects with 32016 units in KwaZulu-Natal, Western Cape, Eastern Cape, Gauteng and North West.
Some of the projects include Mountain Ridge in Paarl, Bridge City at KwaMashu in Durban, Marang Estate in Mahikeng as well as Bokone Social Housing in North West and Housing Association East London, among others.
Van Staden said SHRA has 48 functional and operational projects with 22638 housing units.
“The project requires intervention amounting to 17 projects,” she said, adding that the blocked and delayed projects amounted to 29.2% of the approved housing projects.
Van Staden said out of the 17 projects, four were “distressed”, requiring administrative matters to be addressed, five were before court under litigation and eight were incomplete projects.
She explained the “distressed” projects as those that were already implemented but faced post-delivery challenges such as tenant management and property management.
“They are under the administration of SHRA,” she said.
Van Staden also said the challenges faced by the projects included high cost escalations, delivery failures due to poor governance and weak oversight.
“We have identified through various internal assessments that grant funding was released before the projects were secured and continued to be stuck,” she said.
According to Van Staden, they were making progress in respect of their plans on the various projects.
She also said there would be a dedicated project management office within SHRA to deal with the unblocking of the projects while the entity implemented its mandate.
“The parties that contributed to any of the challenges will be held to account appropriately,” said Van Staden.
Among the priority projects that needed immediate focus were Bridge City, Mountain Ridge, Marang Estate, Bokone and Midrand Heights.
Van Staden also said the first phase will focus on completion of the incomplete structures.
“The amount required to complete the structure is R659 million.
All the incomplete projects will undergo integrity assessment to determine the cost to fix the housing units.
“Our discussion is looking at suspending or partially suspending new approvals in terms of projects and reducing the grant funding.”
She was adamant that all the 17 projects involving about 9400 units would be resolved by December 2028.
“We are confident all matters that are before court should have reached the finalisation stage as at December 2028. The project management office should be in operation by that date,” she said.
“We have been engaging the National Housing Builder Registration Council to do assessments,” she said.
Van Staden also said the second phase would finalise the litigation at the affected projects using the SHRA existing budget.
MK Party MP Thulani Gamede raised concern about the planned suspension of the approval of projects that are in the pipeline.
“Redirecting funding will limit the resolution of legacy failures because you are creating a risk in long-term housing supply momentum,” Gamede said.
Board chairperson Tumisho Makafane said the option on the table to unblock the projects did not mean they would focus solely on stalled and delayed projects.
“We will also do work in the background to ensure we get new projects, address all issues that were identified to cause the projects to be blocked and make sure everything is above so that we produce new pipeline projects when we are in a state of readiness,” Makafane said.
He added that they needed to put together a business case talking to the years outside the Medium Term Budget Framework.
Makafane assured the MPs that consequence management would be instituted.
“We will make sure that we institute the necessary consequence management processes through all legal processes and policies of SHAR and also placing reliance on other legislative documents such as the Public Finance Management Act to deal with fruitless expenditure,” he said.